2022 Road Improvement Project:
Milling, Paving and drainage upgrades
5/9/2022: Milling Meadow Court, Jewel Court, Starkey Place & Montgomery Avenue (from Westminster Drive to Fawn Drive)
5/10/2022: Finish milling Montgomery Avenue & Konner Avenue (from Gathering Road to Woodmont Road)
5/11/2022: Paving Meadow Court, Jewel Court, Starkey Place & Montgomery Avenue
5/12/2022: Paving Konner Avenue
5/16/2022: Striping work
New Maple Avenue Resurfacing Project (NJDOT Grant):
Milling, Paving, curb repairs, inlet repairs on New Maple Avenue (from Hook Mountain Road to Interstate 80 East Ramp)
5/13/2022: Milling Operations
5/14/2022: Paving Operations
5/16/2022: Striping Work