2022 Road Improvement Project:

Milling, Paving and drainage upgrades

5/9/2022:  Milling Meadow Court, Jewel Court, Starkey Place & Montgomery Avenue (from Westminster Drive to Fawn Drive)

5/10/2022:  Finish milling Montgomery Avenue & Konner Avenue (from Gathering Road to Woodmont Road)

5/11/2022:  Paving Meadow Court, Jewel Court, Starkey Place & Montgomery Avenue

5/12/2022:  Paving Konner Avenue

5/16/2022:  Striping work

 

New Maple Avenue Resurfacing Project (NJDOT Grant):

Milling, Paving, curb repairs, inlet repairs on New Maple Avenue (from Hook Mountain Road to Interstate 80 East Ramp)

5/13/2022:  Milling Operations

5/14/2022:  Paving Operations

5/16/2022:  Striping Work